Days 1–30: know the project
- Read the contract's scope, schedule, change and billing clauses.
- Learn the drawing set: sheet index, disciplines, details and schedules.
- Read Division 01, especially submittals, substitutions, closeout and any sustainable design requirements.
- Learn the folder structure and naming and file everything the same day.
- Start keeping meeting notes in the minutes format.
Days 31–60: run the logs
- Own the submittal register: build it from the specs and track review.
- Write RFIs with references and a proposed answer.
- Keep the change order log current and know how a change order request is priced.
- Track procurement and lead times against the schedule.
Days 61–90: money and closeout
- Understand the schedule of values and help prepare the pay application.
- Track lien waivers by vendor and payment.
- Start collecting closeout documents from approved submittals.
- Learn how retainage is released.
| Skill | Good looks like |
|---|---|
| Submittals | Packages complete on first submission, register current weekly |
| RFIs | One question, references, proposed answer, impact noted |
| Changes | Notice sent on time, every change logged |
| Billing | Pay app backup ready before the cutoff |
| Records | Anyone can find the current document in seconds |
Varni trains project engineers on these skills using your templates: see project engineer training.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
What is the difference between a project engineer and a project manager?
Project engineers usually handle documentation and coordination: submittals, RFIs, logs and meeting minutes. Project managers own the contract, budget, schedule and client relationship, and supervise the project engineers.
What software should a new PE learn?
Whatever your company and its clients use: typically a project management platform, PDF markup software, spreadsheets and scheduling software. The documentation principles stay the same across tools.
How can a new PE get faster?
Use templates, file as you go, review logs on a fixed weekly schedule, and ask for feedback on the first few submittals and RFIs.