What makes an RFI work
- One question per RFI. Several questions in one RFI get partial answers and stall.
- Exact references. Sheet, detail, grid line, room number and specification section.
- A picture. A marked-up snip of the conflict is worth a paragraph of description.
- A proposed answer. Suggest a solution the designer can approve with one word.
- Impact stated. Note whether the answer may affect cost or schedule.
- A needed-by date tied to the schedule, not an arbitrary deadline.
Example structure
| Field | Example |
|---|---|
| Subject | Conflict between duct and beam at grid C-4, Level 2 |
| Reference | M-201, detail 4/S-301, spec 23 31 13 |
| Question | The 24x14 supply duct shown on M-201 conflicts with the beam at C-4. Please confirm a revised route. |
| Proposed answer | Reroute below the beam with two 45° offsets as sketched, maintaining a 9 ft ceiling. |
| Impact | Possible added cost and one day; pricing to follow if approved. |
| Needed by | Ductwork at Level 2 starts next Monday |
Questions that should not be RFIs
- Answers already in the documents. Search the specs and details first; unnecessary RFIs cost credibility.
- Requests for approval of a substitution: those usually follow the substitution procedure in Division 01.
- Commercial questions about price or payment: those belong in correspondence or change order requests.
Run a clean RFI log
Track number, subject, date sent, ball-in-court, needed-by date, date answered and any cost or time impact. Review open RFIs in every project meeting, and distribute answers to the field the day they arrive.
When the answer adds work
If an RFI response changes your scope, send notice and a change order request promptly, referencing the RFI number. An RFI answer alone is usually not authorization to bill extra.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
How long should an RFI response take?
Your contract or Division 01 may set a review period. If it does not, agree on typical turnaround times at the start of the project and note urgent RFIs clearly.
Who should write RFIs, the field or the office?
The field usually spots the issue; the project engineer or project manager writes the RFI so the references, wording and log stay consistent.
Can an RFI be used to request a change?
An RFI asks a question. If the answer changes your work, follow up with a change order request under your contract's change procedure.