How to write a change order request that gets approved

A change order request has one job: make it easy for the general contractor to say yes. That means sending it on time, showing exactly what changed, and backing up every dollar and every day.

Varni · Updated · 7 min read

1. Send notice first

Most subcontracts require written notice of a change, or of a claim for more money or time, within a set number of days of the event. Missing it can weaken or waive your right to be paid. Send a short notice letter as soon as you see the change, even before pricing, and keep proof that it was received.

2. Describe the change precisely

  • What changed: the bulletin, revised drawing, RFI answer or directive, with numbers and dates.
  • Why it is a change: how it differs from your bid documents and contract scope.
  • What you will do: the added, deleted or modified work, by location.

3. Price it with backup

CostBackup the GC expects
LaborHours by trade and rate; daily time-and-material tickets for work already done
MaterialQuantities and supplier quotes or invoices
EquipmentRental quotes or rates and hours
Lower-tier subcontractorsTheir priced quotes
Overhead and profitPercentages allowed by your subcontract
Bond and insuranceOnly if your contract allows them on changes

4. State the time impact

If the change affects your schedule, say so in the request with the number of days and why. A change order signed without time can be read as accepting the original completion date.

5. Make it easy to approve

  • One change per request, numbered in your change order log.
  • A one-page summary on top, backup behind it.
  • A clear validity period for your price.
  • Exclusions stated, such as overtime, permits or out-of-sequence work.

6. Follow it to signature and billing

Track every request in a log: date sent, amount, status and response. Follow up weekly. When it is signed, add it to your schedule of values and bill it on the next pay application.

Common reasons change orders get rejected

  • Notice sent late, or not at all.
  • Work that was arguably in the original scope or "inferable" from the documents.
  • Lump-sum pricing with no breakdown.
  • Markups higher than the contract allows.
  • No time-and-material tickets signed by the GC for directed work.

We do this all day

Stuck on this? Email us.

Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.

Email Varni

Opens your email app with a short draft. Add a line and attach PDFs.

Questions we hear

What is the difference between a change order request and a change order?

A change order request (also called a proposed change order or COR) is your priced proposal for a change. A change order is the signed agreement that modifies your contract sum or time. Only signed change orders should be billed.

What if the GC directs us to proceed before pricing is agreed?

Get the direction in writing, track all costs as time and material from the start, and submit pricing as soon as possible. Your contract may describe this as a change directive and set rules for how it is priced.

What markup can I include?

Whatever your subcontract allows. Many contracts set overhead and profit percentages on changes, sometimes different for self-performed and lower-tier work. Read the change clause before pricing.

Work with Varni

Bring Varni onto your next project.

Send the drawings, the deadline and where you need help. We reply with a clear scope, a project-specific fee and a start date.

or write to ravid@varni-ventures.com No set prices · Proposal in 48–72 hours