AIA, G702 and G703 are names associated with the American Institute of Architects. "AIA-style" describes the common billing layout; use the licensed forms when your contract requires them.
The two parts
- G702, Application and Certificate for Payment: the summary page, signed and often notarized, showing the amount due this period.
- G703, Continuation Sheet: the detail behind it, one row per line of your schedule of values.
The continuation sheet (G703), column by column
| Column | Name | How it is calculated |
|---|---|---|
| A | Item number | Line number from the schedule of values |
| B | Description of work | The scope of each line |
| C | Scheduled value | The dollar value of that line; all lines add up to the contract sum to date |
| D | Work completed, from previous application | Total of D and E from last month |
| E | Work completed, this period | Value of work put in place since the last application |
| F | Materials presently stored | Stored materials not yet installed and not included in D or E |
| G | Total completed and stored to date | D + E + F, with percent complete = G ÷ C |
| H | Balance to finish | C − G |
| I | Retainage | Retainage on that line, where the rate varies by line |
The summary page (G702)
- Original contract sum.
- Net change by change orders, approved changes only.
- Contract sum to date = 1 + 2.
- Total completed and stored to date, column G total.
- Retainage, on completed work and on stored materials.
- Total earned less retainage = 4 − 5.
- Less previous certificates for payment.
- Current payment due = 6 − 7.
- Balance to finish, including retainage = 3 − 6.
Our free pay application calculator does this math from your schedule of values.
Retainage
Retainage is the part of each payment the GC holds until the work is complete, commonly 5% to 10% and set by your contract. Some contracts and states reduce it after a milestone such as 50% complete, and many states limit how much can be held on public projects. Track it on every application and request its release with your closeout package.
How to get paid faster
- Know the cutoff. Many GCs want pencil drafts several days before month end.
- Bill what is in place. Overbilling invites rejection and erodes trust.
- Bill approved changes on their own lines. Never mix pending changes into base lines.
- Attach everything. Lien waivers, stored-material invoices and certificates the GC requires.
- Check the math. Every column must reconcile with last month's application.
- Follow up. Confirm receipt and approval, and ask about payment dates.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
What is the difference between G702 and G703?
G702 is the application and certificate for payment: the one-page summary of contract sum, work completed, retainage, previous payments and the current amount due. G703 is the continuation sheet: the line-by-line schedule of values with progress for each item.
Do I have to use official AIA forms?
Only if your contract requires them. The official G702 and G703 documents are published and licensed by the American Institute of Architects. Many GCs accept their own forms or portal entries in the same format. Check your subcontract.
Can I bill for materials stored on site?
Often yes, if your contract allows it. GCs usually ask for invoices, proof of insurance and sometimes photos, and may require storage on site or in a bonded warehouse.
Why was my pay application rejected?
Common reasons are percentages higher than the work in place, unapproved change orders billed, missing lien waivers, math errors, and submitting after the cutoff date.