The four common types
| Waiver | Effective when | Typical use |
|---|---|---|
| Conditional progress | Only once the stated payment clears | Submitted with a monthly pay application |
| Unconditional progress | Immediately on signing | After the progress payment is received |
| Conditional final | Only once final payment clears | Submitted with the final pay application |
| Unconditional final | Immediately on signing | After final payment, including retainage, is received |
The basic rule
Sign conditional waivers before you are paid and unconditional waivers only after the funds have cleared. An unconditional waiver signed early can waive your lien rights for that amount even if the payment never arrives.
Read the waiver language
- Through date: the waiver should cover work through a specific date, not "all work to date" in a final waiver signed early.
- Amount: it should match the payment, not the total contract.
- Exceptions: list unpaid retainage, pending change orders and disputed amounts if the form allows.
- State forms: some states require statutory waiver forms; others allow any form. Use what your contract and state require.
Collecting lower-tier waivers
Owners and general contractors often require waivers from your subcontractors and major suppliers, too. Track them in a waiver log by vendor and payment so a missing waiver does not hold up your own pay application.
| Vendor | Pay app | Amount | Conditional received | Unconditional received |
|---|---|---|---|---|
| Supplier A | #3 | $12,400 | Yes | Pending |
| Subcontractor B | #3 | $28,750 | Yes | Yes |
Lien law varies by state and changes over time. This guide is general information, not legal advice; check your state's requirements with an attorney.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Can I sign an unconditional waiver to get paid faster?
It is risky. If the payment does not clear, you may have waived your rights for that amount. Offer a conditional waiver instead, and exchange the unconditional waiver once funds clear.
Does a lien waiver waive change order claims?
It can, depending on the wording. List pending change orders and claims as exceptions where the form allows, and read the release language carefully.
Who keeps track of waivers?
Usually the project manager or project accountant. A simple log by vendor and payment period prevents missing waivers from delaying payments.