How retainage works
Each billing period, the owner or general contractor withholds a percentage of the amount earned. The percentage is set by the contract, commonly 5% to 10%, and some states limit retainage on certain projects. The withheld amount accumulates until a defined milestone, usually substantial or final completion.
Retainage on the pay application
| G702-style line | What it shows |
|---|---|
| Total completed and stored to date | Everything earned so far |
| Retainage | The percentage withheld on completed work and stored materials |
| Total earned less retainage | What has actually been paid or is payable |
| Less previous certificates | Amounts already billed |
| Current payment due | This period's payment |
See the AIA-style pay application guide or try the pay application calculator.
Retainage reductions
Some contracts reduce retainage once the job reaches a certain percentage complete, or release it early for trades that finish first. Read the retainage clause, and ask for the reduction in writing as soon as you qualify.
What usually holds retainage up
- Incomplete closeout documents: O&M manuals, warranties, as-builts.
- Open punch list items.
- Missing final lien waivers, from you and your subcontractors and suppliers.
- Unsettled change orders or back charges.
- Attic stock and owner training not documented.
A release checklist
- Confirm the release milestone and required documents in the contract.
- Submit the closeout binder early, not after the punch list.
- Close punch items and get written sign-off.
- Collect final waivers from every lower tier.
- Submit a final pay application requesting retainage, with all backup attached.
- Follow up weekly until payment is received.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Is retainage held on stored materials?
Often yes, at the same or a different rate. The contract decides; check the retainage clause and the pay application instructions.
Can a subcontractor be paid retainage before the whole project is finished?
Some contracts allow early release for trades that finish early. If yours does not, ask; owners sometimes agree once the trade's closeout documents are accepted.
What if retainage is withheld after everything is complete?
Document your completion, closeout submissions and requests in writing, and review the prompt payment and retainage rules in your contract and state. Legal remedies vary by state.