Requirements come from Division 01 (often sections such as 01 77 00, 01 78 23, 01 78 36 and 01 78 39) and the closeout article in each technical section. Numbering varies by project; check your spec index.
Binder contents
Front matter
- Cover with project, GC, your company and contract number
- Table of contents by specification section
- Contact list for your company, suppliers and service providers
Operation and maintenance data
- Approved product data for every installed item
- Manufacturer operation and maintenance instructions
- Maintenance schedules and parts lists
Warranties
- Manufacturer warranties with model and serial numbers where required
- Your installer or contractor warranty on company letterhead
- Start dates tied to substantial completion, unless the contract says otherwise
Tests and certifications
- Start-up reports
- Test, balancing and inspection reports
- Certificates the specifications or authorities require
Record documents
- As-built drawings showing installed locations and changes
- Record specifications, if required
Turnover items
- Attic stock list with signed receipt
- Keys, tools and special equipment receipts
- Owner training agendas and sign-in sheets
Financial closeout
- Punch list complete and signed off
- All change orders signed and billed
- Final pay application including retainage
- Final lien waivers, including from your suppliers and lower-tier subs where required
- Any consent of surety the contract requires
Start on day one
Create the binder folders when the job starts. File each approved submittal, warranty and report the day it arrives. When the punch list is done, the binder is too. Need help? See our closeout binder service.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
How long does closeout take?
It depends on how much was collected during the job. If approved submittals, warranties and test reports were filed as they happened, assembling the binder can be quick. If not, chasing documents can take weeks.
What is attic stock?
Extra materials the specifications require you to leave with the owner for future repairs, such as spare ceiling tiles, filters or fixtures. Quantities are set in the specs; get a signed receipt when you deliver them.