Why submittals exist
Construction drawings and specifications describe what the building needs: performance, materials, sizes, standards. They usually do not name the exact product that will arrive on the truck. Submittals close that gap. Before buying or fabricating, the contractor shows the design team exactly what they intend to provide, and the design team checks that it meets the intent.
Done well, submittals catch problems on paper, when they are cheap to fix. Done badly, they delay orders for long-lead equipment and push the schedule.
The main types of submittals
| Type | What it is | Example |
|---|---|---|
| Product data | Manufacturer cut sheets, catalog pages and performance data, marked to show the selected model and options | A lavatory cut sheet with the model, faucet and carrier highlighted |
| Shop drawings | Drawings prepared by the contractor showing how the work will be built and installed | Ductwork layout with sizes, elevations and hangers |
| Samples | Physical pieces of a finish or material for selection or approval | A laminate or paint color sample |
| Informational submittals | Certificates, test reports, qualifications and manufacturer instructions | An installer qualification letter |
| Closeout submittals | Documents turned over at the end of the project | O&M manuals, warranties and record drawings |
Where submittal requirements live in the spec
In projects organized by CSI MasterFormat, two places matter:
- Division 01, Section 01 33 00 Submittal Procedures sets the rules for the whole project: format, numbering, how many copies, the transmittal form, review time and resubmittal rules.
- Part 1 of each technical section has a "Submittals" or "Action Submittals" article that lists exactly what that section requires, such as product data, shop drawings, samples or certificates.
Closeout requirements usually sit in the 01 77 00 and 01 78 00 sections. Numbering varies by project, so always check the spec index first.
How the submittal process works
- Register. At the start of the job, list every submittal the specs require, with numbers and due dates.
- Prepare. The subcontractor or supplier assembles the package: transmittal, marked product data or drawings, and anything else Part 1 calls for.
- GC review. The general contractor checks completeness and coordination, then forwards it.
- Design review. The architect or engineer reviews it and returns it with a review stamp and comments.
- Act on the result. Release for purchase, revise and resubmit, or provide what is missing.
Common mistakes
- Submitting a whole product catalog page without marking the selected model.
- Leaving out items Part 1 of the section requires, such as certifications or warranty letters.
- Submitting shop drawings before the product data they depend on is approved.
- Not tracking review time, so long-lead equipment is released late.
Our product data submittal checklist covers what reviewers look for.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Who prepares construction submittals?
The subcontractor or supplier responsible for the work prepares them. The general contractor reviews them for completeness and coordination, then forwards them to the architect or engineer.
Who approves submittals?
The architect or engineer of record reviews them for general conformance with the design intent. The contractor stays responsible for quantities, dimensions, means and methods, and coordination with other trades. The exact wording is set by your contract and Division 01.
How long does submittal review take?
The review period is set in the contract or Section 01 33 00, commonly measured in working days per review. Check your project's Division 01 and plan long-lead items around it.
What is a submittal register?
A list of every submittal the specs require, built at the start of the job, with numbers, spec sections, responsible party and due dates. Our free submittal log is a simple way to keep one.