The five common review actions
Stamp wording varies by architect, engineer and contract. Always read your project's Section 01 33 00 and the stamp itself. These are the most common actions and what they usually mean.
| Stamp | Usually means | What to do |
|---|---|---|
| Approved No exceptions taken · Reviewed | No comments. The submittal appears to conform to the design intent. | Release for purchase or fabrication. Keep the stamped copy for closeout. |
| Approved as noted Make corrections noted · Furnish as corrected | Acceptable if you make the corrections written on it. | Incorporate every note into the order. Resubmit for record if the spec requires it. |
| Revise and resubmit Amend and resubmit | Not acceptable as submitted; corrections are significant enough to see again. | Do not order. Fix every comment, cloud the changes, increase the revision number and resubmit. |
| Rejected Not approved | The product or approach does not meet the requirements. | Select a different product or approach and submit a new package. |
| For record only Received · Not reviewed | Informational item received for the file; no approval implied. | Log it. Nothing else is needed unless comments are attached. |
How to respond to a returned submittal
- Log the result the day it arrives, with the date and the stamp, in your submittal log.
- Read every comment, including notes on individual pages, not just the stamp.
- Tell the supplier immediately if the result affects an order or lead time.
- Respond to each comment in a short cover letter or response table when you resubmit.
- Cloud and date the changes so the reviewer can find them quickly.
How to avoid revise-and-resubmit in the first place
- Mark the exact model and options on every cut sheet; strike what does not apply.
- Answer every requirement in Part 1 of the section.
- List deviations from the spec up front instead of hoping they are missed.
- Match every item to the tag on the drawing schedule.
See the full product data submittal checklist.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Can I order material on an 'approved as noted' submittal?
Usually yes, as long as you incorporate every note. Read your contract and Section 01 33 00: some projects also require you to resubmit a corrected copy for record.
Does an approved submittal change the contract?
Generally no. Most specs state that review does not relieve the contractor of meeting the contract documents, and that a deviation must be called out specifically to be accepted. Check the language in your Division 01 and contract.
What should I do if a stamp is unclear?
Ask in writing. Send an RFI or a question through the submittal workflow asking the reviewer to clarify, and log the response before ordering.