1. Transmittal and cover
- Project name and number, as written on the contract.
- Submittal number in the project's format, with revision number.
- Spec section number and title.
- List of enclosed items, each with its drawing schedule tag.
- Contractor review stamp or signature if Section 01 33 00 requires one.
2. Spec compliance
- Every requirement in Part 2 (Products) of the section addressed.
- Manufacturer is one the spec lists, or a substitution request is attached.
- Every item Part 1 lists under submittals is included: product data, certificates, test reports, warranties, qualifications.
- Referenced standards and listings shown where the spec names them.
3. Marked-up cut sheets
- Exact model or catalog number selected on each sheet.
- Size, capacity, voltage, phase, finish, color and options selected.
- Items that do not apply are struck through.
- Each sheet labeled with its schedule tag and the spec paragraph it answers.
- Markings readable in black and white.
4. Coordination
- Dimensions and weights checked against the space and structure shown.
- Electrical data matches what the electrical drawings provide.
- Connections and sizes match the piping or duct drawings.
- Accessibility mounting heights and clearances checked where they apply.
5. Deviations and questions
- Every difference from the spec or drawings listed on the transmittal, not buried in the data.
- Open questions asked in the submittal or through an RFI, not left for the reviewer to find.
6. Before you send
- One combined, bookmarked PDF in the order of the transmittal.
- File name in the project's format.
- Logged with the date sent and the review due date in your submittal log.
Short on time? We prepare and track packages to this checklist. See our submittal management service.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
How many products should go in one submittal?
Follow Section 01 33 00. Most projects want one submittal per spec section, so related items are reviewed together, and some split large sections by system or schedule. Avoid mixing sections in one package unless the spec allows it.
Should I highlight or circle the selected options?
Either, as long as it is unmistakable and survives being scanned or printed in black and white. Many teams highlight the selection and strike through what does not apply.