Before the first billing: set up the schedule of values
The schedule of values (SOV) breaks your contract sum into line items you will bill against. Get it approved early. Separate labor and material where the contract allows, and avoid front-loading that the reviewer will reject.
The monthly steps
- Check the billing calendar. Confirm the period end date and the submission deadline. Missing the cutoff usually means waiting another month.
- Walk progress with the field. Agree percent complete by line item with your superintendent or foreman, using photos and quantities where possible.
- Update the continuation sheet. Enter work completed this period for each line (the G703-style sheet).
- Add approved change orders. Only executed changes go on the application, each on its own line.
- Bill stored materials if the contract allows, with invoices, photos and insurance or bill of sale. See stored materials billing.
- Calculate retainage at the contract rate on completed work and stored materials. See retainage explained.
- Complete the summary page. The G702-style summary rolls up the totals, previous payments and current payment due.
- Attach waivers and backup. Your conditional waiver, lower-tier waivers, certified payroll if required, and any backup the contract lists.
- Check, sign and notarize if required, then submit through the required portal or email.
- Follow up. Confirm receipt, answer questions quickly and track the payment due date.
A monthly checklist
| Check | Why it matters |
|---|---|
| Totals match the SOV and approved changes | Reviewers reject math that doesn't tie out |
| Percent complete agreed with the field | Overbilling gets the whole application returned |
| Previous application amounts carried correctly | Errors here compound every month |
| Retainage at the contract rate | Wrong retainage is a common rejection reason |
| Every required waiver attached | Missing waivers hold payment |
| Submitted before the cutoff | Late applications wait a full cycle |
Use the free calculator
Our pay application calculator turns your schedule of values and percent complete into continuation sheet lines, retainage and the amount due, so you can check your math before you submit.
Want it handled every month? Varni prepares AIA-style pay applications for subcontractors and general contractors.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
When should a pay application be submitted?
By the date in your contract or the GC's billing calendar, often a few days before the end of the month. Ask for the calendar at the start of the job.
Can I bill for work not yet installed?
Only stored materials, and only if the contract allows it and you provide the required backup. Billing ahead of progress usually gets the application rejected.
Do I need to use the official AIA forms?
Only if your contract requires them. Many projects accept an AIA-style format with the same summary and continuation sheet structure.