How to prepare a construction pay application, step by step

A pay application is a monthly request for payment backed by evidence. Prepared the same way every month, it gets approved faster and leaves less room for the owner or general contractor to hold money back.

Varni · Updated · 8 min read

Before the first billing: set up the schedule of values

The schedule of values (SOV) breaks your contract sum into line items you will bill against. Get it approved early. Separate labor and material where the contract allows, and avoid front-loading that the reviewer will reject.

The monthly steps

  1. Check the billing calendar. Confirm the period end date and the submission deadline. Missing the cutoff usually means waiting another month.
  2. Walk progress with the field. Agree percent complete by line item with your superintendent or foreman, using photos and quantities where possible.
  3. Update the continuation sheet. Enter work completed this period for each line (the G703-style sheet).
  4. Add approved change orders. Only executed changes go on the application, each on its own line.
  5. Bill stored materials if the contract allows, with invoices, photos and insurance or bill of sale. See stored materials billing.
  6. Calculate retainage at the contract rate on completed work and stored materials. See retainage explained.
  7. Complete the summary page. The G702-style summary rolls up the totals, previous payments and current payment due.
  8. Attach waivers and backup. Your conditional waiver, lower-tier waivers, certified payroll if required, and any backup the contract lists.
  9. Check, sign and notarize if required, then submit through the required portal or email.
  10. Follow up. Confirm receipt, answer questions quickly and track the payment due date.

A monthly checklist

CheckWhy it matters
Totals match the SOV and approved changesReviewers reject math that doesn't tie out
Percent complete agreed with the fieldOverbilling gets the whole application returned
Previous application amounts carried correctlyErrors here compound every month
Retainage at the contract rateWrong retainage is a common rejection reason
Every required waiver attachedMissing waivers hold payment
Submitted before the cutoffLate applications wait a full cycle

Use the free calculator

Our pay application calculator turns your schedule of values and percent complete into continuation sheet lines, retainage and the amount due, so you can check your math before you submit.

Want it handled every month? Varni prepares AIA-style pay applications for subcontractors and general contractors.

We do this all day

Stuck on this? Email us.

Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.

Email Varni

Opens your email app with a short draft. Add a line and attach PDFs.

Questions we hear

When should a pay application be submitted?

By the date in your contract or the GC's billing calendar, often a few days before the end of the month. Ask for the calendar at the start of the job.

Can I bill for work not yet installed?

Only stored materials, and only if the contract allows it and you provide the required backup. Billing ahead of progress usually gets the application rejected.

Do I need to use the official AIA forms?

Only if your contract requires them. Many projects accept an AIA-style format with the same summary and continuation sheet structure.

Work with Varni

Bring Varni onto your next project.

Send the drawings, the deadline and where you need help. We reply with a clear scope, a project-specific fee and a start date.

or write to ravid@varni-ventures.com No set prices · Proposal in 48–72 hours