The common reasons and the fix for each
| Reason | What happened | Fix |
|---|---|---|
| Overbilling | Percent complete ahead of what the reviewer saw | Agree progress with the field and attach photos or quantities |
| Math doesn't tie out | Continuation sheet and summary page disagree | Check totals and previous amounts before signing |
| Unexecuted change orders billed | A pending change was added to the application | Bill only signed changes; track pending ones separately |
| Missing waivers | Your conditional waiver or a lower-tier waiver is missing | Keep a waiver log by vendor and payment |
| Wrong retainage | Rate or reduction applied incorrectly | Check the retainage clause and any approved reductions |
| Stored materials without backup | No invoices, photos or insurance | Attach the backup your contract requires |
| Late submission | Missed the billing cutoff | Get the billing calendar and submit early |
| Wrong format | Not the form, portal or notarization required | Confirm requirements at the first billing |
Build a monthly routine
- Set a reminder a week before every billing cutoff.
- Walk progress with the field and agree percentages.
- Update the continuation sheet and add only executed changes.
- Collect waivers before you finish, not after.
- Check the math, then submit early and confirm receipt.
If it comes back anyway
Ask exactly what needs to change, fix only that, and resubmit the same day if possible. Keep the reviewer's comments with the application so the same issue doesn't repeat next month.
Varni prepares pay applications every month so they go out complete and on time. Try the free pay application calculator to check your numbers.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Can a GC hold my whole payment over one line item?
It depends on the contract. Often reviewers approve the undisputed amount and hold the disputed line. Ask for a partial approval rather than a full rejection.
How do I avoid overbilling disputes?
Base percent complete on something measurable, such as installed quantities, and share photos with the application.
Should pending change orders appear anywhere?
Keep them in your change order log and report them separately. Only executed changes belong on the application.