The two pages at a glance
| Summary page (G702-style) | Continuation sheet (G703-style) | |
|---|---|---|
| Purpose | The request for payment | The detail behind the request |
| Level | Totals for the whole contract | Line by line, per the schedule of values |
| Shows | Contract sum, change orders, completed to date, retainage, previous payments, current payment due | Scheduled value, previous work, this period, stored materials, total completed, percent, balance, retainage per line |
| Signed by | Contractor, often notarized; certified by the architect or reviewer | Supports the summary; not usually signed separately |
How the numbers connect
- The continuation sheet totals work completed and stored to date across all lines.
- That total carries to the summary page.
- The summary page subtracts retainage and previous payments.
- The result is the current payment due.
If the two pages don't tie out, the application comes back. Always check the continuation sheet totals against the summary before you sign.
Where change orders go
Approved change orders appear on the summary page as net changes to the contract sum, and as their own lines on the continuation sheet so progress on each change can be billed separately.
Reviewers check these first
- Percent complete against what they saw on site.
- Previous totals matching the last approved application.
- Retainage at the contract rate.
- Change orders that are actually executed.
G702 and G703 are names associated with the American Institute of Architects. "AIA-style" describes the common layout; Varni is not affiliated with AIA.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Is G703 the same as a schedule of values?
The continuation sheet is built from the schedule of values, adding columns for progress, stored materials, percent complete and retainage each period.
Can subcontractors use the same format?
Yes. Many general contractors ask subcontractors for applications in the same structure so they roll cleanly into the GC's own billing.
What if the architect changes my percent complete?
Ask what they observed, provide photos or quantities, and agree the number. Then carry the approved figure forward so the next month starts from the right baseline.