Subcontract scope of work exhibit: what to include

Most scope disputes start with a vague subcontract. A clear scope exhibit lists exactly which documents, work and responsibilities the subcontractor has agreed to, so gaps are settled before work starts, not during it.

Varni · Updated · 7 min read

1. List the contract documents

Name every drawing sheet, specification section and addendum by number and date. "Per plans and specs" is not enough; a list shows exactly what was priced.

2. Describe the work included

  • Scope by specification section, plus any work shown on drawings outside those sections.
  • Specific inclusions that often cause arguments: hoisting, cutting and patching, sleeves, firestopping, temporary protection, cleanup, testing.
  • Alternates and unit prices accepted, with amounts.

3. State the exclusions

Write exclusions plainly, and make sure each excluded item is covered somewhere else: by another subcontractor, by you, or by the owner.

4. Define the interfaces

InterfaceQuestion to answer in writing
FirestoppingWho seals penetrations through rated assemblies?
Equipment settingWho rigs, sets and connects owner or vendor equipment?
Controls and wiringWho provides and who installs low-voltage wiring?
PatchingWho patches and paints after other trades?
TestingWho arranges, pays for and attends tests and inspections?

5. Schedule, submittals and documentation

  • Mobilization, milestones and the master schedule the subcontractor must follow.
  • Submittal requirements and due dates, tied to long-lead items.
  • Daily reports, safety documentation and meeting attendance.
  • Closeout deliverables: O&M manuals, warranties, as-builts, attic stock and training.

6. Flow-down terms

Carry down the requirements of your own contract that apply to the subcontractor: insurance, notice periods for changes and claims, retainage, billing dates and lien waiver requirements. Review the language with your attorney; the scope exhibit should match the commercial terms, not contradict them.

7. Billing structure

Attach or require a schedule of values that matches your own, so the subcontractor's pay applications roll cleanly into yours.

We do this all day

Stuck on this? Email us.

Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.

Email Varni

Opens your email app with a short draft. Add a line and attach PDFs.

Questions we hear

Is a scope exhibit a legal document?

It is part of the subcontract, so yes. Varni drafts scope and commercial exhibits; legal review of contract language should stay with your attorney.

Should the subcontractor's proposal be attached?

Attaching it can import their exclusions. Many contractors instead write their own scope exhibit and state that it governs over the proposal. Decide with your attorney.

How detailed should it be?

Detailed enough that someone new to the job could tell who is responsible for every interface item without asking.

Work with Varni

Bring Varni onto your next project.

Send the drawings, the deadline and where you need help. We reply with a clear scope, a project-specific fee and a start date.

or write to ravid@varni-ventures.com No set prices · Proposal in 48–72 hours