How a change flows
- The owner or architect issues a bulletin, directive or RFI answer.
- The contractor asks affected subcontractors and suppliers to price it.
- Their pricing is reviewed and leveled, then rolled into the contractor's change order request to the owner.
- The owner approves an owner change order.
- The contractor issues matching subcontract change orders.
Where gaps appear
| Gap | How it happens | How to prevent it |
|---|---|---|
| Scope | The owner change describes the work differently from the sub change | Write sub changes from the approved owner change wording |
| Price | Sub pricing accepted before the owner approves | Issue sub changes after, or conditional on, owner approval |
| Markup | Markup allowed on sub work differs between contracts | Check both change clauses before pricing |
| Time | Owner grants days but subs are not given the same relief | Carry schedule impact both ways |
| Billing | Owner change billed before the sub change is executed | Update both schedules of values together |
Pricing the roll-up
Your request to the owner typically includes your own cost, each subcontractor's price, and the markups your prime contract allows on self-performed and subcontracted work. Show subcontractor pricing as backup; owners and architects expect to see it.
Keep one linked log
Track each change once, with its owner change number and every related subcontract change number, amounts in and out, status and billing period. A linked log shows instantly whether you have approved costs not yet recovered from the owner.
Directed work before approval
When the owner directs work before price is agreed, track time and material for your own forces and require the same from subcontractors, with daily tickets signed by the field. That record becomes the backup for both change orders.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Should we issue a subcontract change before the owner approves?
It depends on your contracts and risk tolerance. Many contractors issue subcontract changes only after owner approval, or make them conditional on it, unless the work is urgent and directed in writing.
Can subcontractors bill a change that the owner has not approved?
Only signed changes should be billed. If you executed a subcontract change before owner approval, you may owe the subcontractor even if the owner has not approved yours.
How do we handle a deductive change?
The same way: price the credit from subcontractors, apply the contract's rules for markup on credits, and issue matching owner and subcontract changes.