Why leveling matters
Quotes arrive with different inclusions, exclusions and qualifications. One supplier includes freight, another does not; one subcontractor excludes testing, another includes it. Comparing raw totals rewards the quote that left the most out.
1. Build a scope matrix
List every scope item down the left, from the specifications and your takeoff, and each bidder across the top. Mark each item included, excluded or unclear.
| Scope item | Bidder A | Bidder B | Bidder C |
|---|---|---|---|
| Base scope per spec section | Included | Included | Included |
| Freight to site | Included | Excluded | Included |
| Testing and start-up | Excluded | Included | Included |
| Permits | Excluded | Excluded | Included |
| Addenda acknowledged | 1–2 | 1 only | 1–2 |
2. Clarify the unclear items
Call or email each bidder about anything unclear, and record the answer. A quote that does not acknowledge the latest addendum needs a written confirmation before you use it.
3. Adjust to a common scope
For every excluded item, add a reasonable cost so each quote covers the same scope. Use another bidder's price for that item, your own estimate, or a budget number, and label the adjustment.
4. Check the qualifications
- Quote validity and escalation clauses.
- Lead times and schedule assumptions.
- Payment terms, retainage and insurance exceptions.
- Substitutions or "or equal" products that may not meet the specification.
5. Compare leveled totals and decide
Choose on leveled cost, scope completeness, schedule and the bidder's record. Write down why you chose one quote; it helps during buyout and if scope questions come up later.
6. Carry the decision into buyout
When you win, the leveled scope becomes the basis for the subcontract scope exhibit or purchase order, so the gaps you found on bid day are closed in writing.
We do this all day
Stuck on this? Email us.
Send us what you have and where you're stuck. Our PMP® and LEED AP BD+C credentialed staff will reply with next steps, and if you'd rather hand it off, a project-specific proposal in 48–72 hours.
Opens your email app with a short draft. Add a line and attach PDFs.
Questions we hear
Should I tell a bidder that their price is high?
You can ask bidders to confirm their scope and check for errors. Sharing competitors' prices is generally poor practice and can damage relationships.
How many quotes should I get?
Enough to compare meaningfully, often three for major scopes, but one well-leveled quote from a trusted partner is better than three you have not reviewed.
What is bid shopping?
Using one bidder's price to pressure another after the bid. Many contractors and trade groups consider it unfair, and it can cost you good bidders.